Owner:  Cedar Hill ISD
Architect: ARMKO Industries Inc.
Delivery Method: Competitive Sealed Proposal
Location:  Cedar Hill, Texas
Description:

Replacement of complete roofing and HVAC systems on 2 school campuses.  This is another “fast track” project that requires removing and replacing 200,000 sf of roofing and flashing as well as 200 RTUs in 12 weeks.  The schedule is further complicated by another contractor performing civil work on the same site during the same period.

Contract Value:

$6.2M

Completion Date:

8/23/2013